KIGEZI UGANDA: The long-awaited Kisoro–Mgahinga and Kabale–Lake Bunyonyi road projects could face another two-year delay, with construction expected to resume in late 2028 as the government undertakes a fresh procurement process to secure a replacement contractor following the termination of the previous contractor’s engagement.
The two roads, measuring 18.1 kilometres and 15.1 kilometres respectively, are part of a tourism infrastructure project worth approximately 30 million US dollars (about Shs112 billion), jointly funded by the African Development Bank (AfDB) and the Government of Uganda through the Ministry of Works and Transport
The Kisoro–Mgahinga Road, which connects Kisoro Municipality to Mgahinga Gorilla National Park, and the Kabale–Lake Bunyonyi Road, which links Kabale Municipality to the popular tourism destination of Lake Bunyonyi, were among the tourism infrastructure projects launched on June 13, 2025, by Deputy Speaker of Parliament Thomas Tayebwa, who represented President Yoweri Kaguta Museveni.
Under the funding arrangement, the African Development Bank contributes 85 percent of the project cost, while the Government of Uganda provides the remaining 15 percent.
Samcrete Engineers and Contractors was initially awarded the construction contract, with the Kisoro–Mgahinga section expected to be completed within 18 months, while the two road projects were scheduled to take approximately 36 months.
However, construction works stalled following disagreements and delays involving the contractor, with only about two percent physical progress reportedly achieved before works were suspended in June 2026.
As of November 22, 2026, it has emerged that the procurement process to secure a new contractor could take up to another two years, potentially pushing the resumption of construction works to late November 2028.
The government subsequently moved to terminate the previous contractor’s engagement and initiate a fresh procurement process to identify a replacement, further delaying the long-awaited road upgrades.
In an exclusive interview with theLens.co.ug, the State Minister for Defence and Veteran Affairs, who is also the Kisoro District Woman Member of Parliament, Hon. Akifeza Grace Ngabirano, attributed the delay to misunderstandings between the government and the contractor responsible for implementing the project, warning that the procurement of a replacement contractor could take up to another two years.
Ngabirano said the government was undertaking the necessary procurement procedures to identify a new contractor who would resume construction under the joint Kabale–Lake Bunyonyi and Kisoro–Mgahinga road upgrade project.
CUE IN MINISTER AKIFEZA ON THE ROAD RR//
Meanwhile, Ngabirano said she had engaged the Ministry of Works and Transport to ensure that routine maintenance is carried out on the affected road sections to improve their condition and ease transportation as the government works towards securing a replacement contractor.
She added that the government remained committed to implementing the project, which is expected to improve regional connectivity, facilitate access to tourism destinations and boost economic activities in the Kigezi sub-region.
CUE IN NGABIRANO ON ROAD MAINTENANCE RR//


Why cant they compensate the project affected people as they wait for contractor. Coz 30% in Kisoro mgahinga haven’t received but were validated while less than 5% kabale bunyonyi still claim compensation.